STAGE 2 BUYERS’ UPDATE
APRIL 2022
![Stage 2](/wp-content/uploads/2022/04/EDM-Image.png)
STAGE 2 UPDATES
Here is this month’s construction update for Stage 2 at Archer’s Way!
- Kerbing works are now complete.
- Retaining walls to lots are now complete.
- Re-spreading of topsoil is 75% complete.
- Roadworks for the internal street are continuing, road gravels have been laid.
- Electrical conduits works are now complete.
- Watermain works are now complete.