Construction Update – July

STAGE 2 & 3 BUYERS’ UPDATE
July 2022

STAGE 2 UPDATES

Check out below the recent construction updates for Stage 2 at Archer’s Way!

  • Roadworks for the internal streets are now complete.
  • Re-spreading of topsoil is now complete.
  • Internal sewer works are complete.
  • External sewer mains connections to cash St are now complete.
  • Installation of electrical pillars is complete.
  • External Power poles along cash street have now been removed.
  • External works along cash street are 95% complete
  • Asphalt and line marking are set to commence in the coming weeks.
  • Landscaping works are set to commence in the coming weeks.

 

STAGE 3 UPDATES

Here is this month’s construction update for Stage 3 at Archer’s Way!

  • The cut and fill of bulk earthwork operations are 90% complete.
  • Retaining walls for lots are 95% complete
  • Sewerage pipework have been installed.
  • Sewerage manholes installation is 90% complete.
  • Major drainage pipework installation is 30% complete.
  • Internal roadworks subgrade compaction and trim to commence in the coming weeks.