STAGE 2 & 3 BUYERS’ UPDATE
July 2022
STAGE 2 UPDATES
Check out below the recent construction updates for Stage 2 at Archer’s Way!
- Roadworks for the internal streets are now complete.
- Re-spreading of topsoil is now complete.
- Internal sewer works are complete.
- External sewer mains connections to cash St are now complete.
- Installation of electrical pillars is complete.
- External Power poles along cash street have now been removed.
- External works along cash street are 95% complete
- Asphalt and line marking are set to commence in the coming weeks.
- Landscaping works are set to commence in the coming weeks.
STAGE 3 UPDATES
Here is this month’s construction update for Stage 3 at Archer’s Way!
- The cut and fill of bulk earthwork operations are 90% complete.
- Retaining walls for lots are 95% complete
- Sewerage pipework have been installed.
- Sewerage manholes installation is 90% complete.
- Major drainage pipework installation is 30% complete.
- Internal roadworks subgrade compaction and trim to commence in the coming weeks.