Archer's Way D'Aguilar - Construction Update May 2021

Construction Update for May 2021

 

We are pleased to bring you this month’s construction update at Archer’s Way.

WORKS COMPLETED TO DATE

  • Commenced clearing and stripping of topsoil to stage 1
  • Bulk earthworks cut to fill activities have commenced
  • External sewer works including construction of sewer manholes has commenced
Constraction update image

PLANNED WORK

  • Complete topsoil strip
  • Continue cut to fill operations
  • Continue external sewer works
  • Commence retaining wall construction