STAGE 2 & 3 BUYERS’ UPDATE
June 2022
STAGE 2 UPDATES
Check out below the recent construction updates for Stage 2 at Archer’s Way!
- Roadworks for the internal streets are now complete.
- Re-spreading of topsoil is 90% complete
- Internal sewer works are complete.
- External sewer mains connections to Cash St are now complete.
- Installation of electrical pillars is complete.
- External Power poles along Cash street have now been removed.
- Rectification works along Cash street have now commenced.
STAGE 3 UPDATES
Here is this month’s construction update for Stage 3 at Archer’s Way!
- The cut and fill of bulk earthwork operations are 80% complete.
- Retaining walls for lots are currently 90% complete
- Sewerage pipework has been installed.
- Sewerage manholes installation has commenced.
- Major drainage pipework installation has commenced.