CONSTRUCTION UPDATE MARCH 2022
There has been lots of progress happening on Stage 2 at Archer’s Way! We are excited to see your new country lifestyle come to life!
STAGE 2 UPDATES
The recent Stage 2 construction updates include:
- The contractor has been continuing with the cut to fill for the bulk earthworks operations now at 95% completion
- Retaining walls to lots are 90% complete
- Stormwater and sewer reticulation works are currently at 70% completion
- Watermain for the internal area is 100% complete
- Roadworks for the internal street has commenced, with road gravels commencing this week