STAGE 2 BUYERS’ UPDATE
May 2022
![](https://archersway.com.au/wp-content/uploads/2022/05/Screen-Shot-2022-05-23-at-1.53.02-pm.png)
STAGE 2 UPDATES
Here is this month’s construction update for Stage 2 at Archer’s Way! The recent heavy rains in the area have caused unfavourable ground conditions for some works, however the contractor has been able to progress with the below:
- Roadworks for the internal streets are now complete.
- Re-spreading of topsoil is 90% complete
- Internal sewer works are complete.
- External sewer mains connections to cash St are 90% complete
- Installation of electrical pillars has commenced.