STAGE 3 BUYERS’ UPDATE
October 2022
STAGE 3 UPDATES
We are pleased to bring you the latest construction update for Stage 3:
- Respreading of topsoil to lots is continuing.
- Water reticulation works are complete.
- Major drainage pipework installation is complete.
- Internal roadworks Basecourse lay has commenced.
- Internal Roadworks Kerbing is 80% complete.
- Installation of the Echidna Culvert Crossing is complete.
- A pre-start meeting has been held with Traffic & Main Roads (TMR) and the external intersection upgrade works will commence in the following weeks.